First Foundations for 1.6GW German Offshore Wind Project Reach Dutch Port
March 14, 2025

The first eight foundations for the Nordeseecluster, a 1.8GW offshore wind project being built in the German North Sea, have arrived and been offloaded in the Dutch base port Eemshaven.
The foundations are around 85 meters long on average and weigh approximately 1,500 tonnes each, the equivalent to the weight of around 800 cars.
Built by RWE, the offshore wind project will consist of Nordseecluster A with 660MW, with commissioning expected in 2027, and Nordseecluster B with additional 900MW to follow in 2029.
A total of 45 of monopile foundations will pass through the Buss Terminal in Eemshaven in 2025 - 44 of them are to carry the wind turbines, and one will support the transformer substation.
The large-scale foundations were manufactured and delivered by Dajin Heavy Industry.
Beginning in summer 2025, the foundations will be shipped from the base port in Eemshaven out to the construction site at sea, which is located around 50 kilometers north of the island of Juist.
The 44 wind turbines for Nordseecluster A will be