DEME to Build Offshore Wind Terminal in German Port
November 28, 2024
![(Credit: DEME)](https://images.maritimeprofessional.com/images/maritime/w600/credit-155054.jpg)
DEME has been awarded a contract, worth up to $52 million, for the construction of an offshore wind terminal in the Port of Cuxhaven in Germany.
The terminal will boost Cuxhaven’s position as a key offshore industrial hub to support the handling of heavy-duty loads, particularly components for offshore wind farms.
Operated by Niedersachsen Ports (NPorts), the expanded offshore wind terminal will consist of three (5-7) berths and 1,250 metres of quay wall for heavy loads, as well as a storage area of 38 hectare.
As part of a consortium, which includes leading German civil marine construction companies Depenbrock and TAGU, DEME will carry out the dredging and land reclamation works, with a total volume of more than 3 million m3 expected to be reclaimed.
Two trailing suction hopper dredgers, a backhoe dredger and several barges will be deployed.
“Construction of the expanded terminal requires an innovative technical approach. The project includes the installation of combi-walls and land reclamation in a dynamic estuarine environment, meeting the complex engineering requirements tailored to a heavy load terminal and demanding geotechnical conditions,” said Lutz Dröge, Area Manager Germany.