Venture Global announced on Friday it had reached first LNG production at the company’s second facility, Plaquemines LNG, in Port Sulphur. "Achieving this milestone for a 20 mtpa nameplate
Because of Venture Global’s unique configuration and construction approach, Plaquemines will produce and export LNG while construction and commissioning continues for the remainder of the project’s 36 trains and associated facilities, the company said.
Commissioning
Venture Global previously said it expects to start LNG production by the end of this year, while commissioning of the facility is expected to last about two years.
The company recently received approval from the US FERC to introduce hazardous fluids to the first liquefaction block at its Plaquemines LNG export plant.
Venture Global’s newbuild carrier, Venture Bayou, also recently arrived at the Plaquemines LNG export plant as the facility nears the launch of its first LNG production.
The 174,000-cbm LNG carrier was on Saturday still located at the LNG plant along the Mississippi River, according to its AIS data provided by VesselsValue.
Prior to this vessel, the Plaquemines LNG facility received a cool-down cargo in August onboard the 2020-built 174,000-cbm, Qogir.
In August, Venture Global secured approval to commission the liquefaction train system block 1 with nitrogen.
To date, the FERC has granted the commissioning of six liquefaction train system blocks.
The company0s first LNG plant, Calcasieu Pass, produced its first LNG on January 19, 2022, moving from FID to LNG production in 29 months, and the first commissioning cargo left the facility on March 1, 2022.
However, the facility is still in commissioning mode, and Venture Global expects to launch commercial operations in 2025.
Energy giants Shell and BP and other firms are in a dispute with Venture Global over the launch of commercial operations at the facility, and they previously launched arbitration proceedings against Venture Global.