Norway’s Equinor shuts Hammerfest LNG terminal

World Maritime

Gassco data showed on Thursday that Hammerfest LNG will be offline until January 9, 2025. LNG Prime invited Equinor to comment on the matter. "After a

partners are currently working on upgrading the facility.

The Snohvit Future project will extend the productive life of Hammerfest LNG past 2030, and includes onshore compression and electrification of Hammerfest LNG.

Equinor and its partners said in December 2022 they would invest 13.2 billion Norwegian krone ($1.16 billion) to upgrade the facility.

In October 2024, Equinor reported an increase in costs for the Snohvit Future project.

Since the PDO (plan for development and operation) the cost increase is 1.9 billion 2024-NOK, Equinor said.

(Updated with a statement by Equinor.)