According to a statement by PV Power, the LNG power plant completed the no-load operation test at 3000 rpm on Wednesday and is ready to be connected to the grid ...
PV Power said in the new statement that the EPC contract is estimated to be over 95 percent complete.
The company said that the Nhon Trach 3 power plant is expected to be put into commercial operation by June 2025.
Deal with PV Gas
PV Power and PV Gas are still working to sign the final gas supply agreement for these plants.
The two firms are taking the final steps to sign the GSA, ensuring a long-term and stable gas source for future operations, PV Power said.
In November last year, PV Gas signed a contract with PV Power to supply the commissioning LNG cargo for the latter’s Nhon Trach 3 and Nhon Trach 4 power plants.
PV Gas launched its Thi Vai LNG terminal on October 29, 2023, after nearly 4 years of construction and commissioning.
This is Vietnam’s first LNG import terminal.
In July 2023, LNG giant Shell delivered the commissioning LNG cargo to the terminal from Indonesia’s Bontang LNG plant.
The Thi Vai LNG import facility consists of one 180,000-cbm LNG tank, a jetty, and regas area.
The terminal has a capacity of 1 mtpa in its first phase, but PV Gas plans to boost the capacity to 3 mtpa in the next stage.
PV Gas recently launched a tender inviting firms to submit bids for four spot LNG cargoes for delivery to the Thi Vai LNG import terminal.