Acteon, through its geo-services brand UTEC, has completed the first year of a three-year balance of plant inspection contract with Siemens Gamesa Renewable Energy…

Acteon, through its geo-services brand UTEC, has completed the first year of a three-year balance of plant inspection contract with Siemens Gamesa Renewable Energy (SGRE) for the 228 MW Butendiek offshore wind farm in Germany.

During the first year, Acteon conducted annual subsea foundation inspections using remotely operated underwater vehicles (ROV), array cable and foundation seabed surveys, and corrosion protection surveys for the wind farm, located approximately 32 km west of the island of Sylt in the German sector of the North Sea.

The work was performed by UTEC, a brand within Acteon’s geo-services business line, and included a multibeam echosounder seabed survey of the array cables and foundation scour.

Additionally, Deepwater, formerly a brand in Acteon’s energy services business line, carried out inspection of the impressed current cathodic protection systems on the turbines along with a subsea CP survey using its POLATRAK DC II reference cell, providing reliable data on the condition of the subsea assets.

These services covered the wind turbine generators and the offshore substation, ensuring the integrity and operational efficiency of the wind farm’s infrastructure.

The services were executed from the Arctic Hunter, a survey vessel provided by OS Energy. A similar vessel will be available in

Content Original Link:

Read full article from Original Source OFFSHORE ENGINEER

" target="_blank">

Read full article from Original Source OFFSHORE ENGINEER

SILVER ADVERTISERS

BRONZE ADVERTISERS

Infomarine banners

Advertise in Maritime Directory

Publishers